Also recorded as: Ajay Engineering Infra Ltd (name as printed by the Times of India, March 2023) · Ajay Engi-Infrastructure Pvt Ltd (then Ajay Engineers)
0
works
0
structures
₹0 cr
awarded value
Being listed as a contractor says nothing by itself about the quality of the work. Companies can respond to any entry through Corrections.
Also called the Rajasthan Circle flyover. According to the Times of India, the R&B Department's Capital Project Division No. 3 approved it in 2019 at an estimated Rs 135.7 crore and AUDA's board agreed on 2 July 2019 to bear half; the cost at inauguration on 5 July 2026 was reported as Rs 175 crore. A March 2023 Times of India report named the contractor of the flyover project as 'Ajay Engineering Infra Ltd'; no source opened confirms that this is the same company as Ajay Engi-Infrastructure Pvt Ltd, whose own project lists do not show this flyover, or that the same firm completed it. The same report said, as part of a wider story about underpasses added to flyover contracts, that the contractor had been assigned an additional Rs 50 crore underpass at the junction without the bidding process; this is the newspaper's account and no official finding is cited. A July 2026 Times of India report said that underpass was never built and is now to be taken up under the SP Ring Road six-laning.
57
Partly evidenced
3 independent outlets report it · No primary document yet, news reports only
Ahmedabad Mirror (28 November 2021) lists a Rs 60.99 crore flyover with work to start in July 2019 and a January 2021 deadline, says it was ready about ten months late and awaiting inauguration by the Chief Minister, and prints the builder as 'Ajay Construction Company'. Ajay Engi-Infrastructure Pvt Ltd lists the Zundal flyover for AUDA at Rs 609.94 million among its own projects (self-reported), which matches that cost. The Times of India reported in October 2019 that the foundation stone was to be laid later that week. The formal opening date was not found.
79
Well evidenced
5 independent outlets report it · Backed by the company's own record
AMC issued the work order in 2015; Vibes of India reports a fixed project cost of Rs 50.88 crore, a tender approved at Rs 39.87 crore and a final bill of Rs 35.55 crore. The contractor's own project list gives a contract amount of Rs 39.87 crore, award date 10 April 2015, completion 30 November 2017 and work done of about Rs 34.68 crore. Media reports quote the cost anywhere from Rs 34 crore to Rs 50 crore (Rs 34, 37, 40, 42 and an 'official' Rs 50 crore). SGS India was the project management consultant. The company name appears in sources both as Ajay Engi-Infrastructure Pvt Ltd and Ajay Engineering Infrastructure Pvt Ltd.
82
Well evidenced
3 independent outlets report it · Backed by the company's own record
Listed in the contractor's own completed-works statement and website with the Additional City Engineer, AMC, as client. The statement shows a contract amount of Rs 40.23 crore against an estimate of Rs 45.41 crore, award on 10 April 2015, a target date of 9 April 2017 and actual completion on 15 October 2017, with a 624.20 m length; the value of work done is given as Rs 37.48 crore, which is also the figure on the firm's website (Rs 374.77 million, completed 2017-18).
58
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Client listed as IL&FS Ltd; four-lane structure on open foundations with reinforced-earth walls. Contract Rs 21.47 crore, value of work done Rs 16.45 crore; dates are from the contractor's completed-works statement (target 24 June 2014). Located at Kalol in Gandhinagar district.
58
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Approach bridges on both sides of the railway span · AMC / Western Railway (builder not stated in source)
Completed
Awarded
2 Jul 2009
Completed
3 Jan 2011
Value
₹23.55 crore
Age
15 yr 11 mo
Client AMC; 1200 mm piles with RCC box girder; Rs 235.46 million, financial year 2010-11 per the contractor's site. Award and completion dates are read from the firm's works statement, whose columns are misaligned, so treat them as approximate. The railway span itself would have been built separately.
58
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Contractor's statement: estimate Rs 21.37 crore, contract Rs 23.24 crore, awarded 17 July 2008, completed 16 June 2010 (the same as the target date), value of work done Rs 18.68 crore; 1200 mm piles with RCC T-beam and PSC box girder. Client: City Engineer, AMC.
58
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Listed on the contractor's own website and project list with AUDA as client (self-reported; no independent source opened): Rs 95.59 million, shown as 2006 on the home page and 2006-07 on the projects page.
55
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Per the contractor's own website and project list (self-reported; no independent source opened): client AMC, Rs 261.45 million, completed in financial year 2011-12; bored piles of 600 to 1500 mm (10,560 running metres) with PSC girders over running track.
51
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Reported as approved on 1 April 2021 with a March 2024 deadline (DeshGujarat; another report says the flyover was first approved in 2017). AMC issued two notices to the contractor over delays in April 2023, and about 5% of work was pending in March 2025. The superstructure was complete and a load test ran in mid-April 2025; an opening date is not confirmed in the sources read. Shifting a high-tension line underground added about Rs 18 crore. In November 2025 Swarajya, citing The Times of India, reported that AMC had withheld payments on this project while seeking to recover the Rs 3.90 crore cost of demolishing the Hatkeshwar flyover from the same contractor.
45
Partly evidenced
4 independent outlets report it · No primary document yet, news reports only
Subway at Soni-ni-Chali junction on NH-8 (for BRTS) · AMC (Ahmedabad Janmarg Ltd)
Completed
Awarded
Not on record
Completed
Not on record
Value
Not disclosed
Age
—
Listed by the contractor as 'sub way at Sini ni chal Junction on NH-8 for BRTS Ahmedabad' for AMC, completed in financial year 2010-11, 1200 mm piles with RCC box. Cost is left blank because the firm's own documents disagree: its website gives Rs 47.5 million, while its completed-works statement shows an estimated cost of about Rs 33.9 crore, a revised contract of Rs 23.5 crore and about Rs 23.55 crore of work done, with award on 2 July 2009 and actual completion on 3 January 2011.
48
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Listed in the contractor's completed-works statement as 'approach ramp on NH-8C from Sola ROB for Science City' for Executive Engineer AUDA, on pile foundations. The value (about Rs 3 crore) and dates cannot be read reliably.
48
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Contractor's site: 'bridge across Sabarmati river on Gandhinagar Koba Arodram [aerodrome] Road near Hasol, Ahmedabad', Rs 364.64 million, financial year 2014-15 (its home page says 2015); 1500 mm piles, 40 m PSC girders. The location matches the Indira Bridge crossing, but the page does not use that name, so whether this is the additional bridge there is unconfirmed.
51
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Listed by the contractor as 'approach on Ring Road near village Tragad for Sardar Patel Ring Road', client Executive Engineer AUDA, Rs 87.31 million, completed in financial year 2009-10, with the feature given as 'Under Pass'.
51
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Cross-drainage works, minor bridges and culverts (AUDA two-lane phase) · AUDA
Completed
Awarded
Not on record
Completed
Not on record
Value
Not disclosed
Age
—
The contractor's completed-works statement lists 'cross drainage work for AUDA Ring Road Link-1 from Aslali NH-8 to Kamod SH-142' and 'minor bridge & culvert at various chainage of Ring Road', both for AUDA. Values and dates cannot be read reliably from the statement because its columns are misaligned.
48
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Client: Gujarat Road and Infrastructure Company Ltd. 18 spans of 30 m with 180 PSC girders launched under live traffic, reinforced-earth approaches and 1,135 m of service road. The contractor's own website gives the cost of work as Rs 686.54 million and the year of completion as 2019-20. Located at Sindbad Junction, Kalol.
51
Partly evidenced
Only one outlet reports it · Backed by the company's own record
Six-laning with flyovers – Package III (elevated corridor section) · R&B Gujarat (National Highway Division) / NHAI
Completed
Awarded
Not on record
Completed
Not on record
Value
₹323 crore
Age
—
Package covers Ch. 31/300–35/480 (4.18 km), the Thaltej–Gota elevated stretch. Ajay Engi-Infrastructure's own website lists this package (NH-147, km 31/300 to 35/480, Package III, EPC, client National Highway Division, Ahmedabad) at Rs 266 crore; no independent source naming the contractor was found, and the tender-results listing does not show the winner. Cost figures differ by source: Rs 249.16 crore (original package value per Times of India, March 2023), Rs 266 crore (contractor's site, a tender-results listing with scheduled completion 25 April 2020, and the Gujarat R&B project page, which showed 100% physical progress as on 24 December 2025) and Rs 322.58 crore (January 2023 status list).
83
Well evidenced
5 independent outlets report it · Backed by an official document