Hatkeshwar (Chhatrapati Shivaji Maharaj) flyover

AMC · Hatkeshwar, between Khokhra and CTM · 0.583 km

A four-lane flyover opened in 2017 that developed repeated surface failures and was closed within five years. Independent tests found poor concrete quality and the AMC eventually ordered it pulled down.

4
works on record
8 yr 11 mo
since it was completed (Nov 2017)
₹96.47 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 4 of 4

    Demolition

    Under construction
    Contract awarded
    2025
    Work started
    Sep 2025
    Completion
    Not on record
    Contract value
    ₹3.9 crore

    Demolition-only tender estimated at Rs 9.31 crore (May 2025) and awarded at Rs 3.90 crore, which the municipal commissioner said would be recovered from the original builder. DeshGujarat names the contractor as Shri Ganesh Construction; Gujarat Samachar calls it Shri Ganesh Corporation, a Mumbai-based company. Reports date the start to 21 August (Swarajya, citing The Times of India) or 24 September 2025 (DeshGujarat); IIT Gandhinagar reviewed the method. About 35% done by mid-November 2025 and about 80% by 8 January 2026, per the standing committee chairman; completion not confirmed in sources read.

  2. Work 3 of 4

    Demolish-and-rebuild tender (not executed)

    Cancelled
    Bidder (not the builder)
    Vishnu Prakash R Punglia Ltd (sole bidder)
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    ₹52.7 crore

    Earlier tenders drew no bidders and one Rs 118 crore bid was rejected. The fourth tender closed on 6 August 2024 with a single Rs 52.7 crore bid; the state said the cost would be recovered from the original contractor. The AMC later switched to a demolition-only tender.

  3. Work 2 of 4

    Closure, testing and action against builder

    Completed
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    2022
    Completed
    Not on record
    Contract value
    Not disclosed

    A temporary closure for a large pothole in March 2021 was followed by full closure in 2022. Tests by institutes including IIT Roorkee and SVNIT Surat reported weak concrete. Per reports, the AMC filed an FIR in April 2023, blacklisted the contractor and the consultant, and suspended several of its own officials; four directors of the contractor were arrested in May 2023.

  4. Work 1 of 4

    Original construction

    Completed
    Contract awarded
    2015
    Work started
    2015
    Completed
    Nov 2017
    Contract value
    ₹39.87 crore
    Age since completion
    8 yr 11 mo

    AMC issued the work order in 2015; Vibes of India reports a fixed project cost of Rs 50.88 crore, a tender approved at Rs 39.87 crore and a final bill of Rs 35.55 crore. The contractor's own project list gives a contract amount of Rs 39.87 crore, award date 10 April 2015, completion 30 November 2017 and work done of about Rs 34.68 crore. Media reports quote the cost anywhere from Rs 34 crore to Rs 50 crore (Rs 34, 37, 40, 42 and an 'official' Rs 50 crore). SGS India was the project management consultant. The company name appears in sources both as Ajay Engi-Infrastructure Pvt Ltd and Ajay Engineering Infrastructure Pvt Ltd.

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Hatkeshwar (Chhatrapati Shivaji Maharaj) flyover.

Snap a photo next time you drive past and be the first to post.