Vehicular underpass at Sindbad intersection, Kalol (km 31+150)
- Awarded
- Not on record
- Started
- Not on record
R&B Gujarat · Adalaj – Kalol – Mehsana (Palavasna Circle) · 51.6 km
The principal road from Ahmedabad to north Gujarat (SH-41), a 51.6 km four-lane toll road with service roads. The state government dates the original four-laning to 1999, while an ICRA note gives its commercial operation date as February 2003; it is now slated for widening to eight lanes.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Client: Gujarat Road and Infrastructure Company Ltd. 18 spans of 30 m with 180 PSC girders launched under live traffic, reinforced-earth approaches and 1,135 m of service road. The contractor's own website gives the cost of work as Rs 686.54 million and the year of completion as 2019-20. Located at Sindbad Junction, Kalol.
Client listed as IL&FS Ltd; four-lane structure on open foundations with reinforced-earth walls. Contract Rs 21.47 crore, value of work done Rs 16.45 crore; dates are from the contractor's completed-works statement (target 24 June 2014). Located at Kalol in Gandhinagar district.
Cabinet approval January 2026: 6.1 km elevated corridor at Kalol, eight flyovers, eight underpasses and a new rail overbridge at Vaghara; tenders to follow, with a two-year build period.
L&T's infrastructure arm states (archived page) that L&T was shareholder and EPC contractor in Ahmedabad-Mehsana Toll Road Company Ltd, an SPV promoted by the Government of Gujarat, and executed the 51.6 km four-lane toll road plus the 11 km Kadi–Kalol spur on SH-41 on a BOT basis; it gives the project value as INR 3.78 billion (Rs 378 crore), including strengthening the old two-lane road and adding service roads, and says L&T exited the SPV in July 2006. An ICRA rating note on Gujarat Road and Infrastructure Company Ltd gives the commercial operation date of the Ahmedabad–Mehsana stretch as 20 February 2003. A January 2026 DeshGujarat report quoting the state government instead says the road was originally built as a four-lane highway in 1999; the two dates are not reconciled in the sources read.