AUDA · Zundal circle, SP Ring Road (north)
Flyover over the Zundal circle on the northern arc of the SP Ring Road. AUDA's board approved it in February 2019 and the foundation stone was scheduled for late October 2019.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Ahmedabad Mirror (28 November 2021) lists a Rs 60.99 crore flyover with work to start in July 2019 and a January 2021 deadline, says it was ready about ten months late and awaiting inauguration by the Chief Minister, and prints the builder as 'Ajay Construction Company'. Ajay Engi-Infrastructure Pvt Ltd lists the Zundal flyover for AUDA at Rs 609.94 million among its own projects (self-reported), which matches that cost. The Times of India reported in October 2019 that the foundation stone was to be laid later that week. The formal opening date was not found.