Dinesh Chamber flyover (Hatkeshwar–Hirawadi road, Bapunagar)
AMC · Dinesh Chamber junction, Bapunagar · 0.624 km
A 624 m PSC box-girder flyover at Dinesh Chamber on the Hatkeshwar–Hirawadi road in Ahmedabad.
Build history
Every construction, widening and repair we could source, newest first.
- CompletedWork 1 of 1
Original construction
- Contractor
- Ajay Engi-Infrastructure Pvt Ltd
- Contract awarded
- 10 Apr 2015
- Work started
- Not on record
- Completed
- 2017
- Contract value
- ₹40.23 crore
- Age since completion
- about 9 years
Listed in the contractor's own completed-works statement and website with the Additional City Engineer, AMC, as client. The statement shows a contract amount of Rs 40.23 crore against an estimate of Rs 45.41 crore, award on 10 April 2015, a target date of 9 April 2017 and actual completion on 15 October 2017, with a 624.20 m length; the value of work done is given as Rs 37.48 crore, which is also the figure on the firm's website (Rs 374.77 million, completed 2017-18).
Checked against sources
Citizen reports
Anonymous photos and notes from people who use this stretch.
No reports yet for Dinesh Chamber flyover (Hatkeshwar–Hirawadi road, Bapunagar).
Snap a photo next time you drive past and be the first to post.