Who Built What
All roads & bridges
FlyoverCompleted

Dinesh Chamber flyover (Hatkeshwar–Hirawadi road, Bapunagar)

AMC · Dinesh Chamber junction, Bapunagar · 0.624 km

A 624 m PSC box-girder flyover at Dinesh Chamber on the Hatkeshwar–Hirawadi road in Ahmedabad.

1
work on record
about 9 years
since last completed (2017)
₹40.23 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 1 of 1

    Original construction

    Completed
    Contract awarded
    10 Apr 2015
    Work started
    Not on record
    Completed
    2017
    Contract value
    ₹40.23 crore
    Age since completion
    about 9 years

    Listed in the contractor's own completed-works statement and website with the Additional City Engineer, AMC, as client. The statement shows a contract amount of Rs 40.23 crore against an estimate of Rs 45.41 crore, award on 10 April 2015, a target date of 9 April 2017 and actual completion on 15 October 2017, with a 624.20 m length; the value of work done is given as Rs 37.48 crore, which is also the figure on the firm's website (Rs 374.77 million, completed 2017-18).

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Dinesh Chamber flyover (Hatkeshwar–Hirawadi road, Bapunagar).

Snap a photo next time you drive past and be the first to post.