Bakrol junction flyover, SP Ring Road
Original construction (ADB Package A: Bakrol, Hathijan, Ramol, Panjrapol) · AUDA
- Awarded
- 23 Aug 2024
- Completed
- Not on record
- Value
- Not disclosed
- Age
- —
Single item-rate contract for four flyovers valued at Rs 391.16 crore in total (ADB lists about USD 45.3 million, contract dated 23 January 2025, under Rajkamal Builders Infrastructure Pvt Ltd); the cost of this bridge alone is not separately reported; a May 2023 TV9 report and a September 2024 DeshGujarat report carried an estimate of Rs 64 crore for Bakrol. The Prime Minister was scheduled to lay the foundation stone on 16 September 2024 and traffic diversions were announced in late December 2024. Award (23 August 2024) and start (1 October 2024) dates and the 1 October 2027 scheduled completion are from an ADB monitoring-report table, which names the contractor as the Rajkamal-Kalthia joint venture.