Hathijan junction flyover, SP Ring Road
AUDA · Hathijan circle, SP Ring Road (south-east)
A six-lane flyover with junction improvements on the eastern arc of the SP Ring Road. One of ten junction structures AUDA planned from 2021 with an Asian Development Bank loan (Ahmedabad Peri-urban Livability Improvement Project); six tenders were approved in September 2022 and later repackaged.
Build history
Every construction, widening and repair we could source, newest first.
- Under constructionWork 1 of 1
Original construction (ADB Package A: Bakrol, Hathijan, Ramol, Panjrapol)
- Contract awarded
- 23 Aug 2024
- Work started
- 1 Oct 2024
- Completion
- Not on record
- Contract value
- Not disclosed
Single item-rate contract for four flyovers (Bakrol, Hathijan, Ramol, Panjrapol) valued at Rs 391.16 crore in total. ADB's monitoring reports name the contractor as the Rajkamal Builders and Kalthia Engineering & Construction joint venture, with letter of award on 23 August 2024, mobilisation on 1 October 2024 and scheduled completion on 1 October 2027; ADB's contracts list shows the contract as dated 23 January 2025, about USD 45.3 million, and names only Rajkamal Builders Infrastructure Pvt Ltd. The cost of this bridge alone is not in the contract documents; a DeshGujarat table of September 2024 gives about Rs 78 crore and 860 m for a junction it prints as 'Elephant' (apparently Hathijan), and a May 2023 TV9 report put Hathijan, Ramol and Panjrapol together at Rs 243 crore. DeshGujarat reported that the Prime Minister was expected to lay the foundation stone on 16 September 2024, and AUDA issued a traffic-diversion notice on 24 December 2024 saying construction would begin soon.
Checked against sources
Citizen reports
Anonymous photos and notes from people who use this stretch.
No reports yet for Hathijan junction flyover, SP Ring Road.
Snap a photo next time you drive past and be the first to post.