Ahmedabad–Dholera Expressway (NE-7 / NH-751)

NHAI · Sarkhej – Sindhrej – Vejalka – Dholera SIR – Adhelai · 109 km

A greenfield access-controlled expressway from Sarkhej on the SP Ring Road to the Dholera Special Investment Region, built in four EPC packages.

4
works on record
7 months
since last completed (Mar 2026)
—
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 4 of 4

    Package 4: Dholera SIR–Adhelai (38 km)

    Completed
    Contract awarded
    2020
    Work started
    Dec 2021
    Completed
    Mar 2026
    Contract value
    Not disclosed
    Age since completion
    7 months

    The January 2023 NHAI status list names the Dineshchandra R Agrawal Infracon – MKC Infrastructure joint venture (appointed 13 December 2021, 28.19% progress); Wikipedia and a May 2024 NHAI under-implementation list (as uploaded to SlideShare) name only Dineshchandra R. Agrawal Infracon Pvt Ltd. For the whole expressway, Wikipedia gives a cost of Rs 3,196 crore excluding land and the 2023 status list a total capital cost of Rs 4,110 crore; no package-level cost was found.

    Checked against sources
  2. Work 3 of 4

    Package 3: Vejalka–Dholera SIR (22.5 km)

    Completed
    Contract awarded
    2020
    Work started
    Jul 2021
    Completed
    Mar 2026
    Contract value
    Not disclosed
    Age since completion
    7 months

    Appointed date 19 July 2021 per the January 2023 NHAI status list (the May 2024 NHAI list uploaded to SlideShare shows 20 July 2021); 22.5% progress in January 2023. Wikipedia gives the award as August 2020 and the expressway's inauguration as 31 March 2026.

    Checked against sources
  3. Work 2 of 4

    Package 2: Sindhrej–Vejalka (26.5 km)

    Completed
    Contract awarded
    2020
    Work started
    Jan 2022
    Completed
    Mar 2026
    Contract value
    Not disclosed
    Age since completion
    7 months

    Appointed date 21 January 2022; 11.7% progress in January 2023. An NHAI under-implementation list dated May 2024 (as uploaded to SlideShare) shows the contractor for this package as Sadbhav Engineering Ltd together with Montecarlo Construction Ltd.

  4. Work 1 of 4

    Package 1: Sarkhej–Sindhrej (22 km)

    Completed
    Contract awarded
    2020
    Work started
    Jan 2022
    Completed
    Mar 2026
    Contract value
    Not disclosed
    Age since completion
    7 months

    Appointed date 11 January 2022; 21.4% progress in January 2023. An NHAI under-implementation list dated May 2024 (as uploaded to SlideShare) shows the contractor for this package as Sadbhav Engineering Ltd together with Montecarlo Construction Ltd.

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Ahmedabad–Dholera Expressway (NE-7 / NH-751).

Snap a photo next time you drive past and be the first to post.