Rail overbridgeUnder construction

Thaltej – Hebatpur railway overbridge (LC 11B)

AMC · Hebatpur, near Sola Science City · 0.679 km

A railway overbridge on the Hebatpur road toward Science City.

1
work on record
—
no completion date on record
₹74.15 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 1 of 1

    Original construction

    Under construction
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    ₹74.15 crore

    Ananta Procon lists this four-lane overbridge (LC 11B on the Ahmedabad–Viramgam line) on its own project page with the AMC as client and a project cost of Rs 74.15 crore. In November 2025 the AMC reported 85% of approach work and 73% of the railway portion complete, with a June 2026 deadline.

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Thaltej – Hebatpur railway overbridge (LC 11B).

Snap a photo next time you drive past and be the first to post.