Superstructure replacement and new parallel two-lane bridges (EPC)
- Awarded
- 2026
- Started
AMC · Ranip / RTO – Shahibaug · 0.454 km
A 1973 beam bridge (about 454 m) over the Sabarmati linking Ranip with Shahibaug. After structural distress in December 2025 the AMC announced an EPC project to replace the superstructure and add new two-lane bridges on each side; by July 2026 the old spans were being torn down.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
AMC announced the EPC plan on 26 December 2025 at an estimated Rs 250 crore. A Rs 232.80 crore tender issued on 3 January 2026 drew a single bid (reported as from 'DR Agarwal') and was to be re-invited; the standing committee approved the project at about Rs 240 crore on 5 March 2026; the 2026-27 draft budget set aside Rs 272 crore; ANI in July 2026 cited Rs 236 crore. Demolition of the old spans began on 1 July 2026. On 25 August 2026 Gujarat Samachar reported that opposition Congress councillors alleged the contract, which they said would reach nearly Rs 300 crore, was given under a single-tender process to Dineshchandra R. Agarwal Infracon, a firm they said had been debarred for 20 years in 1997; the municipal commissioner replied that the debarment, imposed by GWSSB, had ended in 2017. The Rs 300 crore figure is the opposition's projection, not an approved amount. Defect liability is 10 years per the January 2026 tender.
Wikipedia says major repairs began in August 2019, with the bridge closed on eight Sundays; a completion date is not given.