Original construction
- Awarded
- Not on record
- Started
- Jan 2019
- Completed
AUDA · Shantipura (Sanand) junction, SP Ring Road (south-west)
Flyover on the SP Ring Road at the Shantipura crossing with the Ahmedabad-Sanand road, including a span over the railway. Work was launched in January 2019.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Ahmedabad Mirror lists a Rs 93.76 crore contract starting January 2019 with a June 2021 deadline; in November 2021 an AUDA official expected completion by March 2022, citing the railway portion. The consultant's site gives a project cost of Rs 81.90 crore. Exact opening date not found; the bridge was in use by 2026.