Sattadhar junction flyover

AMC · Sattadhar crossroads, Ghatlodia · 0.975 km

A four-lane flyover at one of the busiest junctions in the western zone.

1
work on record
6 months
since last completed (29 Mar 2026)
₹104 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 1 of 1

    Original construction

    Completed
    Contract awarded
    Apr 2023
    Work started
    Not on record
    Completed
    29 Mar 2026
    Contract value
    ₹104 crore
    Age since completion
    6 months

    Ananta Procon lists the four-lane Sattadhar flyover on its own project page with the AMC as client and a project cost of Rs 81.39 crore. The AMC standing committee approved the tender in mid-April 2023 at Rs 81.49 crore (18.35% above the Rs 68.85 crore estimate) with a 24-month period and a three-year defect-liability period for civil works, which the opposition contested; a later report says the tender was briefly withdrawn when the period was raised to five years and then reverted. Cost was reported as Rs 103.63 crore in November 2025 and about Rs 90 crore at the inauguration on 29 March 2026.

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Sattadhar junction flyover.

Snap a photo next time you drive past and be the first to post.

Sattadhar junction flyover · Who Built What