Original construction (ADB Package 5)
- Awarded
- 16 Jan 2024
- Started
AUDA · Ognaj circle, SP Ring Road (north-west) · 0.741 km
A six-lane underpass at Ognaj junction with 741 m of approaches and a 46 m box, plus parallel concrete service roads. One of ten junction structures AUDA planned from 2021 with an Asian Development Bank loan (Ahmedabad Peri-urban Livability Improvement Project); six tenders were approved in September 2022 and later repackaged.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Item-rate contract of Rs 64.92 crore (about USD 7.75 million on ADB's list, dated 31 July 2024) with a 24-month period. Physical progress was about 6% at end-2024 and about 30% by mid-2025 per ADB monitoring reports. Award/start dates are from an ADB report table.