Ognaj junction underpass, SP Ring Road

AUDA · Ognaj circle, SP Ring Road (north-west) · 0.741 km

A six-lane underpass at Ognaj junction with 741 m of approaches and a 46 m box, plus parallel concrete service roads. One of ten junction structures AUDA planned from 2021 with an Asian Development Bank loan (Ahmedabad Peri-urban Livability Improvement Project); six tenders were approved in September 2022 and later repackaged.

1
work on record
—
no completion date on record
₹64.92 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 1 of 1

    Original construction (ADB Package 5)

    Under construction
    Contract awarded
    16 Jan 2024
    Work started
    8 Jul 2024
    Completion
    Not on record
    Contract value
    ₹64.92 crore

    Item-rate contract of Rs 64.92 crore (about USD 7.75 million on ADB's list, dated 31 July 2024) with a 24-month period. Physical progress was about 6% at end-2024 and about 30% by mid-2025 per ADB monitoring reports. Award/start dates are from an ADB report table.

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Ognaj junction underpass, SP Ring Road.

Snap a photo next time you drive past and be the first to post.