Rakesh Construction Co
1 work across 1 asset · ₹64.92 crore in sourced contract value
Under construction
- Awarded
- 16 Jan 2024
- Completed
- Not on record
- Value
- ₹64.92 crore
- Age
- —
Item-rate contract of Rs 64.92 crore (about USD 7.75 million on ADB's list, dated 31 July 2024) with a 24-month period. Physical progress was about 6% at end-2024 and about 30% by mid-2025 per ADB monitoring reports. Award/start dates are from an ADB report table.
Checked against sources