Income Tax circle flyover
AMC · Income Tax crossroads, Ashram Road · 0.805 km
An 805 m flyover over the Income Tax junction on Ashram Road with parking beneath.
Build history
Every construction, widening and repair we could source, newest first.
- CompletedWork 1 of 1
Original construction
- Contractor
- Ranjit Buildcon Ltd
- Contract awarded
- Not on record
- Work started
- Not on record
- Completed
- 3 Jul 2019
- Contract value
- ₹57.5 crore
- Age since completion
- 7 yr 3 mo
When expansion-joint bolts worked loose in December 2025, the AMC said the repair was being done by Ranjit Buildcon Ltd, the contractor that built the bridge, at its own cost under the guarantee period. Per the opposition's figures the cost rose from an estimated Rs 59.59 crore to Rs 65.91 crore after the design went from four to five lanes; retaining the Gandhi statue beneath the flyover is said to have added about Rs 10 crore. The Times of India also lists this flyover among AMC projects that ran late.
Citizen reports
Anonymous photos and notes from people who use this stretch.
No reports yet for Income Tax circle flyover.