AMC · IIM Road, Vastrapur (between IIM old and new campus gates) · 0.551 km

A 551 m two-lane east-west flyover on IIM Road in west Ahmedabad, running between the two IIM-Ahmedabad campus gates.

1
work on record
—
no completion date on record
₹38.69 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 1 of 1

    Original construction

    Completed
    Contract awarded
    Not on record
    Work started
    30 Jul 2012
    Completed
    Not on record
    Contract value
    ₹38.69 crore

    DeshGujarat (January 2014) names the builder as Dineshchandra R Agrawal Infracon Pvt Ltd and gives a start date of 30 July 2012. The 15-month contract should have finished in October 2013; the deadline slipped to 26 January 2014, with late pile and dynamic load testing cited. Inauguration by the chief minister was expected on 3 February 2014; the actual opening date is not confirmed in the sources read. Rs 38.69 crore is described as the estimated cost.

    Checked against sources

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for IIM Road flyover.

Snap a photo next time you drive past and be the first to post.