Original construction
- Awarded
- Jan 2019
- Started
AUDA · Naroda-Dehgam crossroads, SP Ring Road (north-east) · 0.743 km
A flyover carrying the SP Ring Road over the Naroda-Dehgam road crossing. Work began in January 2019 and was held up for about two years because overhead high-tension power lines had not been moved.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Work order issued January 2019 for Rs 60.33 crore with a December 2020/January 2021 deadline. The Times of India reported in December 2022 that construction stopped midway because of unshifted GETCO lines and attributed the lapse to AUDA's consultants and supervising engineers. A CEPT student report names Multi Media Consultants as PMC. Completion date not found; treat status as unverified after 2022.