Completed
- Awarded
- Not on record
- Completed
- Dec 2020
- Value
- ₹33 crore
- Age
- 6 years
Ahmedabad Mirror reported that the redevelopment was awarded to PSP Projects and completed in December 2020, with HCP as design and tendering consultant; it put the project at Rs 38 crore, against the Rs 33 crore announced earlier. The same report described a dispute over five-year streetlight operation and maintenance, for which the AMC separately engaged Citelum India. A first sample stretch was shown in April 2019.
79
Well evidenced
3 independent outlets report it · Backed by the company's own record
- Status: Confirmed in source
- Contractor: Confirmed in source
- Start date: Confirmed in source
- Completion: Confirmed in source
- Contract value: Confirmed in source