Konkan Railway Corporation Ltd – Fuji Silvertech Concrete Pvt Ltd JV

1 work across 1 asset · ₹830 crore in sourced contract value

Road

Kharicut Canal redevelopment corridor (road over covered canal)

Phase 2: SP Ring Road – Naroda Muktidham, and Vinzol – Ghodasar – Vatva – Khari river (22.4 km) · AMC (50:50 funding with Gujarat irrigation department)

Upcoming
Awarded
4 Dec 2025
Completed
Not on record
Value
₹830 crore
Age
—

DeshGujarat (5 December 2025) reported that the AMC standing committee approved the award on Thursday, 4 December 2025, at Rs 829.92 crore plus GST, 15.25% below an estimate of Rs 1,061.43 crore (the same report also cites an estimate of Rs 979.26 crore plus GST), covering about 22.415 km. The state had sanctioned Rs 1,003 crore for phase 2 in March 2025. Physical start is not confirmed in the sources read.

Checked against sources