Highway
CompletedBagodara-Tarapur-Vasad highway (SH-8) six-laning
Package I: Bagodara-Tarapur (53.8 km) on modified annuity · GSRDC / R&B Gujarat
- Awarded
- Not on record
- Completed
- 19 Feb 2022
- Value
- ₹649 crore
- Age
- 4 yr 9 mo
CARE Ratings records a 16.5-year concession with GSRDC, project cost Rs 649.21 crore (Rs 196.10 crore construction grant), provisional COD on 19 February 2022 and final completion in mid-2022 (the rationale gives both 9 June and 2 July 2022). Formally dedicated on 22 April 2022.
75
Well evidenced
2 independent outlets report it · Backed by an official document
- Status: Confirmed in source
- Contractor: Confirmed in source
- Completion: Confirmed in source
- Contract value: Confirmed in source