Contractor
IRB Ahmedabad Vadodara Super Express Tollway Pvt Ltd (IRB Infrastructure Developers)
1 work across 1 asset · ₹4,880 crore in sourced contract value
Ahmedabad–Vadodara Expressway (NE-1)
Upgrade to six lanes with service roads (DBFOT concession, together with NH-8 six-laning) · NHAI
- Awarded
- 25 Jul 2011
- Completed
- Not on record
- Value
- ₹4,880 crore
- Age
- —
25-year DBFOT concession signed with NHAI on 25 July 2011, held by IRB Ahmedabad Vadodara Super Express Tollway Pvt Ltd, covering 93.3 km of expressway plus 102.3 km of NH-8. Rs 4,880 crore is the project cost stated by IRB for the whole concession; Wikipedia cites about Rs 3,300 crore for the upgrade. Sources disagree on scope: Wikipedia says IRB won a bid to upgrade the expressway from four to six lanes with service lanes, while IRB's own project page describes six-laning of the NH-8 section and improvement of the existing expressway as a four-lane carriageway. IRB's page lists the project under ongoing concessions and gives no completion date.