Science City (Bhadaj) junction flyover and underpass, SP Ring Road

AUDA · Bhadaj circle / Science City junction, SP Ring Road (north-west)

A six-lane, 27 m wide flyover at Bhadaj (Science City) circle on the SP Ring Road, planned together with an underpass beneath it. Amit Shah opened the flyover on 26 September 2022.

3
works on record
4 years
since last completed (26 Sep 2022)
₹77.8 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 3 of 3

    Themed public space under the flyover

    Upcoming
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    Not disclosed

    In May 2023 AUDA's board approved a Science City-themed design for the space below the flyover, proposed by the Gujarat Council of Science City.

    Checked against sources
  2. Work 2 of 3

    Underpass beneath the flyover

    Under construction
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    ₹4.47 crore

    A 45 m underpass estimated at Rs 4.47 crore could not be built with the flyover because AMC handed over the land late; in mid-2023 AUDA's general body approved the contractor's request for a 7% price variation rather than re-tendering. AUDA's February 2024 budget still listed the work; completion not confirmed.

  3. Work 1 of 3

    Flyover construction

    Completed
    Contractor
    Not on public record
    Contract awarded
    Jul 2019
    Work started
    Not on record
    Completed
    26 Sep 2022
    Contract value
    ₹73.33 crore
    Age since completion
    4 years

    AUDA approved the Rs 73.33 crore flyover on 2 July 2019 with an original completion date of 1 February 2022; the foundation stone was planned for late October 2019. The project consultant's site quotes Rs 67.84 crore and a 434 m flyover of 14 spans. Contractor not named in the sources read.

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Science City (Bhadaj) junction flyover and underpass, SP Ring Road.

Snap a photo next time you drive past and be the first to post.