Sabarmati barrage-cum-bridge (Acher – Camp Sadar Bazar)

SRFDCL · Acher (west bank) – Camp Sadar Bazar (east bank), Riverfront Phase 2 · 1.048 km

A six-lane bridge with an air-filled rubber barrage beneath it, being built as part of Sabarmati Riverfront Phase 2.

2
works on record
—
no completion date on record
₹294 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 2 of 2

    Air-filled rubber barrage supply, installation and maintenance

    Under construction
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    ₹53.78 crore

    Contract covers manufacture, supply, installation and maintenance of the air-filled rubber barrage and its automation system. Rubber membrane installation was to begin after civil work, post-monsoon 2026.

    Checked against sources
  2. Work 1 of 2

    Civil construction of bridge

    Under construction
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    ₹240 crore

    Civil contract (tender value Rs 239.92 crore) awarded by SRFDCL. The central span is described as a 126 m iron arch. As of March 2025 the diaphragm wall and riverbed filling were under way, with completion expected by April 2027.

    Checked against sources

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Sabarmati barrage-cum-bridge (Acher – Camp Sadar Bazar).

Snap a photo next time you drive past and be the first to post.