Omnagar–Chamanpura railway underpass (LC 3)
Western Railway / AMC · Omnagar – Chamanpura (Asarwa–Himmatnagar line) · 0.265 km
A limited-height subway, 265 m long and 8.5 m wide, replacing level crossing no. 3 between Omnagar and Chamanpura on the Asarwa–Himmatnagar railway section. The box was pushed under the live tracks.
Build history
Every construction, widening and repair we could source, newest first.
- Under constructionWork 1 of 1
Limited-height subway by box pushing
- Contractor
- Not on public record
- Contract awarded
- Not on record
- Work started
- Not on record
- Completion
- Not on record
- Contract value
- ₹19 crore
Cost about Rs 19 crore. The Railway Minister asked for completion before Navratri 2026 and the divisional railway manager set 30 September 2026 as the target; utility shifting by AMC and Torrent Power was the remaining dependency. Contractor and start date not given; single-source.
Checked against sources
Citizen reports
Anonymous photos and notes from people who use this stretch.
No reports yet for Omnagar–Chamanpura railway underpass (LC 3).
Snap a photo next time you drive past and be the first to post.