FlyoverCompleted

Odhav junction flyover, SP Ring Road

AUDA · Odhav crossroads, SP Ring Road (east)

Flyover carrying the SP Ring Road over the Odhav junction in east Ahmedabad. AUDA opened it to the public in January 2019.

2
works on record
7 yr 9 mo
since last completed (8 Jan 2019)
₹65.93 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 2 of 2

    Surface repair (with Bhat and Vatva bridges)

    Upcoming
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    ₹14 crore

    AUDA earmarked Rs 14 crore in April 2025 for resurfacing three ring-road bridges at Bhat, Odhav and Vatva; the figure covers all three. Whether the Odhav portion has been executed is not confirmed.

    Checked against sources
  2. Work 1 of 2

    Original construction

    Completed
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    2013
    Completed
    8 Jan 2019
    Contract value
    ₹51.93 crore
    Age since completion
    7 yr 9 mo

    AUDA announced the public opening for Tuesday 8 January 2019. Ahmedabad Mirror (Nov 2021) put the cost at Rs 51.93 crore and said the project, begun in 2013-14, ran about 24 months late. Contractor not named in the sources read.

    Checked against sources

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Odhav junction flyover, SP Ring Road.

Snap a photo next time you drive past and be the first to post.