Who Built What
All roads & bridges
BridgeCompleted

Nehru Bridge

AMC · Ashram Road – Lal Darwaja · 0.95 km

A Sabarmati road bridge opened in the early 1960s that carries heavy traffic between Ashram Road and the old city.

2
works on record
5 yr 6 mo
since last completed (Apr 2021)
₹3.75 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 2 of 2

    Bearing and expansion-joint replacement

    Completed
    Contract awarded
    Not on record
    Work started
    Mar 2021
    Completed
    Apr 2021
    Contract value
    ₹3.25 crore
    Age since completion
    5 yr 6 mo

    Deck lifted about 50 mm with hydraulic jacks; 126 of 144 bearings replaced during a roughly 45-day closure. Divya Bhaskar (June 2021) reported that the tender was allotted to Sanfield (India) Ltd at 29.20% below estimate and approved at Rs 2.54 crore on 16 September (year not stated), and that extra repair items added Rs 1.19 crore, which was put to the standing committee; the report gives the resulting cost as Rs 3.86 crore in its headline and Rs 3.73 crore in its text. Wikipedia quotes Rs 3.25 crore and says the bridge reopened by late April 2021.

  2. Work 1 of 2

    Original construction

    Completed
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    1956
    Completed
    1962
    Contract value
    ₹0.5 crore
    Age since completion
    about 64 years

    Foundation stone laid in 1956; Construction World says the estimated cost at that time was Rs 50 lakh (an estimate, not a final cost). Wikipedia says the bridge was inaugurated around 1962 and an AMC list quoted by DeshGujarat dates it to 1962, while Construction World called it 61 years old in March 2021.

    Checked against sources

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Nehru Bridge.

Snap a photo next time you drive past and be the first to post.