Law Garden – CN Vidyalaya (Panchvati) flyover
AMC · Law Garden – Panchvati crossroads – Ambawadi circle – CN Vidyalaya · 0.77 km
A 770 m flyover planned across Panchvati crossroads on the Law Garden–CN Vidyalaya route.
Build history
Every construction, widening and repair we could source, newest first.
- Under constructionWork 1 of 1
Original construction
- Contractor
- Not on public record
- Contract awarded
- Feb 2025
- Work started
- May 2025
- Completion
- Not on record
- Contract value
- ₹142 crore
Part of a Rs 379 crore two-flyover package with a 34-month timeline. After an earlier single-bid tender was cancelled, the AMC combined this flyover and the Chimanbhai Patel parallel bridge into one Rs 226 crore tender, which the standing committee approved in the third week of February 2025 at Rs 267.30 crore with a 36-month period for Panchvati, a five-year defect-liability period and long performance bonds for bearings and expansion joints. The winning contractor is not named in the reports read.
Checked against sources
Citizen reports
Anonymous photos and notes from people who use this stretch.
No reports yet for Law Garden – CN Vidyalaya (Panchvati) flyover.
Snap a photo next time you drive past and be the first to post.