Original construction
- Awarded
- 15 Oct 2022
- Started
- Jul 2022
AUDA · Kamod circle, SP Ring Road (south) · 1.157 km
A six-lane flyover, 1,157 m long and 27 m wide, over Kamod circle on the SP Ring Road. Amit Shah laid its foundation stone in July 2022.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Foundation stone laid 24 July 2022 at a stated Rs 77.71 crore. The Times of India reported that AUDA tendered it at Rs 87.44 crore, that the work order was given to the contractor on 15 October 2022 and that, at a 2 May 2023 board meeting, AUDA revised the scope (10.5 m RCC service road instead of 9 m asphalt), lifting the cost to Rs 95.14 crore and extending the deadline. A May 2025 Gujarati Jagran report still listed it among bridges being built. Contractor not named. The start date shown is the foundation-stone month.