Rail overbridgeCompleted

Jagatpur railway overbridge (Vandemataram crossing)

AMC / Western Railway · Jagatpur – Gota (Vandemataram railway crossing) · 0.735 km

A 735 m railway overbridge replacing the Vandemataram level crossing, linking Gota, Chandlodia and Jagatpur with SG Highway. Its funding was split between the state, the railways and a private developer.

1
work on record
3 yr 4 mo
since last completed (20 Jun 2023)
₹67.66 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 1 of 1

    Original construction

    Completed
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    Not on record
    Completed
    20 Jun 2023
    Contract value
    ₹67.66 crore
    Age since completion
    3 yr 4 mo

    Cost is given as both Rs 67.66 crore and about Rs 70 crore. The state was to bear 50% and the railways 25%; developer Siddhi Developers' share was cut from about Rs 16.91 crore to a Rs 7 crore advance after the pandemic, per DeshGujarat. In November 2021 the AMC was promising completion within a year; it opened on 20 June 2023. Deck reported as 735.26 m long and 8.40 m wide. Civil contractor not named.

    Checked against sources

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Jagatpur railway overbridge (Vandemataram crossing).

Snap a photo next time you drive past and be the first to post.