Who Built What
All roads & bridges
BridgeCompleted

Indira Bridge (Hansol–Bhat, Ahmedabad–Gandhinagar road)

R&B Gujarat (Capital Project Division) · Hansol / Airport – Bhat, over the Sabarmati

The six-lane Sabarmati crossing on the airport road between Ahmedabad and Gandhinagar, described by Sandesh as about 43 years old. It was widened from four to six lanes in 2012-14 and is now planned to become a 12-lane crossing.

3
works on record
9 months
since last completed (Jan 2026)
₹133 cr
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 3 of 3

    Expansion to 12 lanes (three added lanes each side, cable-stayed design)

    In tender
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    Not on record
    Completion
    Not on record
    Contract value
    ₹96.23 crore

    Sandesh and DeshGujarat (15 July 2026) both report an R&B tender of Rs 96.23 crore (overall estimate about Rs 109 crore) for two new three-lane cable-stayed bridges, one on each side, with 2.5 m footpaths and viewing galleries, targeted for completion within a year. Award and contractor not found.

    Checked against sources
  2. Work 2 of 3

    Technical audit and expansion-joint clarification

    Completed
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    Not on record
    Completed
    Jan 2026
    Contract value
    Not disclosed
    Age since completion
    9 months

    After media reports of cracks, engineers of Capital Project Division-3 inspected the bridge and the government said an audit by Infinite Consultant (a consultant, not a works contractor) found the structure sound.

    Checked against sources
  3. Work 1 of 3

    Widening from four to six lanes

    Completed
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    Sep 2012
    Completed
    Jun 2014
    Contract value
    ₹37 crore
    Age since completion
    12 yr 4 mo

    Deck width went from 18.10 m to 28.50 m, per a reply by the roads and buildings minister in the Gujarat Assembly on 16 July 2014. Contractor not named.

    Checked against sources

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Indira Bridge (Hansol–Bhat, Ahmedabad–Gandhinagar road).

Snap a photo next time you drive past and be the first to post.