Expansion to 12 lanes (three added lanes each side, cable-stayed design)
- Awarded
- Not on record
- Started
- Not on record
R&B Gujarat (Capital Project Division) · Hansol / Airport – Bhat, over the Sabarmati
The six-lane Sabarmati crossing on the airport road between Ahmedabad and Gandhinagar, described by Sandesh as about 43 years old. It was widened from four to six lanes in 2012-14 and is now planned to become a 12-lane crossing.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Sandesh and DeshGujarat (15 July 2026) both report an R&B tender of Rs 96.23 crore (overall estimate about Rs 109 crore) for two new three-lane cable-stayed bridges, one on each side, with 2.5 m footpaths and viewing galleries, targeted for completion within a year. Award and contractor not found.
After media reports of cracks, engineers of Capital Project Division-3 inspected the bridge and the government said an audit by Infinite Consultant (a consultant, not a works contractor) found the structure sound.
Deck width went from 18.10 m to 28.50 m, per a reply by the roads and buildings minister in the Gujarat Assembly on 16 July 2014. Contractor not named.