- UpcomingWork 2 of 2
Bearing replacement and strengthening (six-ROB package)
- Contractor
- Not on public record
- Contract awarded
- Feb 2026
- Work started
- Not on record
- Completion
- Not on record
- Contract value
- Not disclosed
DeshGujarat (9 February 2026) reported that the AMC had approved a Rs 63 crore tender for bearing replacement on six railway overbridges including Cadila, following post-Gambhira inspections, and that the lower of two bidders had been selected; the bidder was not named. PropNewsTime describes the same approval as Rs 62.79 crore for four overbridges. This is a package cost, not the cost for this bridge. Unrelated to this, the bridge's central BRTS lane was shut at night from 6 April to 30 May 2025 for bullet-train segment erection, and a November 2025 police notification said the restriction would continue because the deadline had been extended to 15 December 2025.
Checked against sources - CompletedWork 1 of 2
Original construction
- Contractor
- Not on public record
- Contract awarded
- Not on record
- Work started
- Not on record
- Completed
- 1996
- Contract value
- Not disclosed
- Age since completion
- about 30 years
Year as listed by AMC in December 2025 (a separate report puts its age at about 29 years in early 2026). Contractor and cost not found.
Checked against sources
Citizen reports
Anonymous photos and notes from people who use this stretch.
No reports yet for Cadila railway overbridge.
Snap a photo next time you drive past and be the first to post.