Bearing replacement and strengthening (six-ROB package)
- Awarded
- Feb 2026
- Started
- Not on record
- Completion
AMC · Ghodasar – Cadila Road – Vatva (Narol–Naroda BRTS corridor)
Railway overbridge on Cadila Road in the Ghodasar area with a BRTS lane down its middle. Segments of the Mumbai–Ahmedabad high-speed rail viaduct were erected on pillars above the bridge in 2025.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
DeshGujarat (9 February 2026) reported that the AMC had approved a Rs 63 crore tender for bearing replacement on six railway overbridges including Cadila, following post-Gambhira inspections, and that the lower of two bidders had been selected; the bidder was not named. PropNewsTime describes the same approval as Rs 62.79 crore for four overbridges. This is a package cost, not the cost for this bridge. Unrelated to this, the bridge's central BRTS lane was shut at night from 6 April to 30 May 2025 for bullet-train segment erection, and a November 2025 police notification said the restriction would continue because the deadline had been extended to 15 December 2025.
Year as listed by AMC in December 2025 (a separate report puts its age at about 29 years in early 2026). Contractor and cost not found.