- Awarded
- 2022
- Started
- Sep 2022
AMC / Western Railway · But Bhavani Mandir crossing, Vejalpur
A three-lane railway overbridge from But Bhavani Mandir in Vejalpur toward Anandnagar, approved in 2022 with the cost shared equally by the railways and the state.
Every construction, widening and repair we could source, newest first. Tap “How we know this” on any entry.
Approved by the AMC road and building committee on 6 September 2022 as a three-lane bridge with the cost split equally between the railways and the state government. In October 2023 DeshGujarat reported the project as Rs 66.76 crore with a 26-month period started in September 2022, and that Vejalpur MLA Amit Thaker had complained to the municipal commissioner that pier foundation work had not begun after a year. A December 2025 Gujarat Samachar table lists the cost as Rs 78.54 crore and the deadline as 30 June 2026. Contractor not named.