Who Built What
All roads & bridges
FlyoverCompleted

Anjali crossroads flyover (Sushma Swaraj flyover)

AMC · Anjali crossroads, Vasna / Paldi · 1.2 km

A four-lane, roughly 1.2 km flyover over Anjali crossroads on the southern extension of Ashram Road, described in 2016 and 2020 as the longest flyover in the city. The AMC named it after Sushma Swaraj in August 2020.

1
work on record
—
no completion date on record
—
total sourced contract value
—
no citizen ratings yet

Build history

Every construction, widening and repair we could source, newest first.

  1. Work 1 of 1

    Original construction

    Completed
    Contractor
    Not on public record
    Contract awarded
    Not on record
    Work started
    26 Jun 2016
    Completed
    Not on record
    Contract value
    Not disclosed

    Ground-breaking was performed by the chief minister on 26 June 2016 together with the Income Tax junction flyover. The flyover was formally named in August 2020; the opening date, cost and civil contractor were not found in sources that could be opened. Jhaveri Associates' portfolio page describes a 16.5 m wide four-lane flyover and names HCPDPM as architect; it does not state Jhaveri's own role.

Citizen reports

Anonymous photos and notes from people who use this stretch.

Rate condition

No reports yet for Anjali crossroads flyover (Sushma Swaraj flyover).

Snap a photo next time you drive past and be the first to post.